KOTA KINABALU, Nov 27 (Bernama) — The first phase of the erection of a temporary Emergency Restoration System (ERS) tower in Ranau was completed at 6.28 pm today, according to Sabah Electricity.

In a statement, the utility company said its technical team would proceed with the second phase to restore the electricity transmission link connecting Sabah’s West Coast and East Coast.

“The restoration work is progressing according to the planned timeline. Despite light rain at the site, the technical team is prioritising the safety of its personnel and adhering to the prescribed procedures at every stage of implementation.

“Sabah Electricity remains committed to expediting the restoration of electricity supply and apologises for any inconvenience caused to consumers,” it said.

The technical team had also completed the installation of anchoring supports for the temporary ERS tower to ensure the stability of the structure, which was erected following the collapse of tower T313 yesterday.

The collapse of tower T313, detected at 6.04 am yesterday, severed two transmission line circuits running from the West Coast to the East Coast of Sabah, disrupting electricity supply across eight districts and affecting 153,599 registered consumers.

Sabah Electricity is targeting to restore electricity supply by Dec 2 or earlier.