99 Federal projects worth RM12 billion approved in Sarawak

KOTA SAMARAHAN: A total of 99 federal development projects worth a total of RM12 billion have been approved in Sarawak, including 35 projects that are currently in the construction phase, said Works Minister Datuk Seri Alexander Nanta Linggi.

“A total of 35 projects are currently in the construction phase with a project value of RM5 billion,” he said at a press conference after the handover ceremony of the completed project of the Muara Tuang Camp Armed Forces Family Home (RKAT) here, today.

He said projects worth RM50 million and below had been handed over to the Sarawak Public Works Department (JKR) for implementation.

Regarding contractor performance, Nanta revealed that his ministry has a complete internal database and records on the level of capability of each contractor appointed, but the list is not officially announced to prevent any abuse.

He explained that no incentives in the form of bonuses or additional work are automatically given to contractors who complete projects ahead of schedule.

“We know in our records which contractors can be categorized as reliable and can be trusted to do the job perfectly, there are also contractors who are not so good,” he said.

Nanta said that delays in a project cannot be placed solely on the shoulders of the contractor because this also involves external factors such as land acquisition, detailed survey work, utility relocation and scope changes.

However, he said the contractor still cannot give up if the delay is due to their own negligence.

“We don’t want this project to be behind schedule or sick because of their management weaknesses, finances or management of manpower and workers in the field. There are many big projects, but there are not many workers, in their area of ​​responsibility, they must be fully responsible,” he said.

Meanwhile, the Muara Tuang Camp RKAT worth RM119.1 million was developed on an area of ​​28.3 acres, involving the construction of 190 residential units of various classes equipped with basic facilities such as a surau, kindergarten and nursery school.

Implemented by the Malaysian Public Works Department’s Special Project Team 2, he said the project was successfully completed within the three-year period as set, although there was a slight extension of time (EOT) following the increase in the scope of work.

— BERNAMA